Eversource S-136 Transmission Line Rebuild Project
Eversource, permit holder for utility lines across the WMNF, has identified 214 existing structures that need to be replaced within the existing right of way (ROW) of the S-136 transmission line in Whitefield, Jefferson, Randolph, and Gorham NH.
Project Summary
Location Summary:
About seven miles of the Whitefield to Berlin (S-136) transmission line in Jefferson, Randolph, and Gorham; Coos County, New Hampshire
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 03/29/2024 |
Decision | 12/2024 (Estimated) |
Implementation | 12/2024 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (22), 36 Cfr 220.6(E)(22)
Special Authority:
Not Applicable / Other
Lead Management Unit:
White Mountain National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management; Facility Management
Project Activity:
Facility Improvements/Construction
Current Status:
Completed
Project Decision Information
Eversource S-136 Transmission Line Rebuild Project
Decision Signed Date: 12/04/2024
Forests:
White Mountain National Forest
Districts:
Androscoggin Ranger District
States:
New Hampshire
Counties:
Coos
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Marianne Leberman
71 White Mountain Drive
Campton, NH 3223
603-466-2713 ext216
marianne.leberman@usda.gov