Burnett Portage Trail
Address severe erosion issues currently existing by installing trail structures that will provide a hardened surface to accommodate the existing and future levels of visitor use.
Project Summary
Current Status:
Completed
Location Summary:
Etolin Island.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 04/12/2012 |
| Decision | 07/2012 (Estimated) |
| Implementation | 05/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (1), 36 Cfr 220.6(E)(1)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Wrangell Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Recreation Management
Project Activity:
Developed Site Management
Project Decision Information
Burnett Inlet Portage Trail Construction
Decision Signed Date: 07/19/2012
Forests:
Tongass National Forest
Districts:
Wrangell Ranger District
States:
Alaska
Counties:
Wrangell-Petersburg
Legal Land Description:
Trail extends between Forest Development Road (FDR) 51401 (Latitude, Longitude: 56.17202N, - 132.47956W, NAD 83) and the north shore of Burnett Inlet (Latitude, Longitude: 56.17026N, - 132.47266W, NA
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Dee Galla
525 Bennett Street
Wrangell, AK 99929-0051
907-874-7551
dgalla@fs.fed.us
Last Updated: 9/26/2012