Lunch Creek Trail Maintenance
Bridge repairs and trail reconstruction on Lunch Creek Trail to reduce trail flooding and protect wetland areas. Work includes handrail replacements, culvert installation, trail tread conversion to boardwalk and step-and-run.
Project Summary
Current Status:
Completed
Location Summary:
On Revillagigedo Island at the northern end of the Ketchikan road system.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 04/24/2023 |
| Decision | 07/2023 (Estimated) |
| Implementation | 07/2023 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (1), 36 Cfr 220.6(E)(1)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Ketchikan Misty Fjords Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Recreation Management
Project Activity:
Trail Management
Project Decision Information
Lunch Creek Trail Maintenance
Decision Signed Date: 07/14/2023
Forests:
Tongass National Forest
Districts:
Ketchikan Misty Fjords Ranger District
States:
Alaska
Counties:
Ketchikan Gateway
Legal Land Description:
T73S R90E Sections 27, 34, 25
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Denise Wolvin
3031 Tongass Avenue
Ketchikan, AK 99901-5743
907-225-2148