2012 Hecla Greens Creek Surface Exploration Drilling Plan of Operations
The Hecla Greens Creek Mining Company plans to continue its surface exploration program in 2012 and proposes limited or minimal tree cutting in the Greens Creek IRA to provide safe helicopter landings and drill pads.
Project Summary
Location Summary:
Admiralty National Monument
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 12/02/2011 |
Comment Period | 04/04/2012 |
Expected Analysis Type:
Environmental Assessment
Categorical Exclusion:
32.2 (8), 36 Cfr 220.6(E)(8)
Special Authority:
Ira - Inventoried Roadless Area Activities Requiring Secretary/Undersecretary Approval
Lead Management Unit:
Admiralty Island National Monument
Notice and Comment Regulation:
215
Project Purpose:
Minerals And Geology
Project Activity:
Minerals Or Geology Plans Of Operations
Current Status:
Completed
Project Decision Information
2012 Hecla Greens Creek Surface Exploration Drill Plan of Operations
Decision Signed Date: 05/11/2012
Legal Notice Date: 06/13/2012
Forests:
Tongass National Forest
Districts:
Admiralty Island National Monument
States:
Alaska
Counties:
Juneau
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Sarah Samuelson
8510 Mendenhall Loop Road
Juneau, AK 99802
907-789-6274
ssamuelson@fs.fed.us
Last Updated: 7/18/2013