North POW Intertie Phase 3
Install and maintain 4.5 miles of power line from Coffman Cove Junction to Naukati Junction.
Project Summary
Location Summary:
FDR 2000 from Coffman Cove Junction to Naukati Junction
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 08/16/2012 |
Comment Period | 08/16/2012 |
Decision | 01/2013 (Estimated) |
Implementation | 02/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Thorne Bay Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
AP&T North POW Intertie Phase 3
Decision Signed Date: 01/08/2013
Legal Notice Date: 01/14/2013
Forests:
Tongass National Forest
Districts:
Thorne Bay Ranger District
States:
Alaska
Counties:
Prince of Wales-Outer
Legal Land Description:
Sections 10 – 13 & 24, T 69S, R 80E, Copper River Meridian
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Melanie Slayton
1312 Federal Way
Thorne, AK 99919-001
907-828-3249
mslayton@fs.fed.us
Last Updated: 1/14/2013