Hollis to Harris Trail CE
This project would improve existing roads between Hollis Day Use Area and Forest Service Harris River Interpretive Trail. The trail is approximately 5 miles long with 1 mile of undeveloped trail.
Project Summary
Location Summary:
Hollis Community Picnic Area to Forest Service maintained Harris River Interpretive Trail--approximately 5 miles
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 11/26/2012 |
Comment Period | 11/26/2012 |
Decision | 05/2013 (Estimated) |
Implementation | 07/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (1), 36 Cfr 220.6(E)(1)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Thorne Bay Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Recreation Management
Project Activity:
Trail Management
Current Status:
Completed
Project Decision Information
Hollis to Harris Trail improvement CE
Decision Signed Date: 05/29/2013
Legal Notice Date: 05/31/2013
Forests:
Tongass National Forest
Districts:
Craig Ranger District
States:
Alaska
Counties:
Prince of Wales-Outer
Legal Land Description:
CRM Township 74 S, Range 83 E, Sections 14-16 and CRM Township 74S, Range 84E, Section 18
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Victoria Houser
1312 Federal Way
Thorne, AK 99919-001
907-826-1614
vhouser@fs.fed.us
Last Updated: 6/25/2013