Port Snettisham Iron Ore Project 2013 Plan of Operations
The 2013 Plan of Operations for surface exploration activities at the Port Snettisham Iron Ore Project proposes helicopter-supported core drilling at nine sites and a temporary camp.
Project Summary
Location Summary:
Township 45 South, Range 72 East, Sections 5, 8, and 9; Copper River Meridian.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 06/05/2013 |
Decision | 01/2015 (Estimated) |
Implementation | 04/2015 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (8), 36 Cfr 220.6(E)(8)
Special Authority:
Ira - Inventoried Roadless Area Activities Requiring Chief's Approval
Lead Management Unit:
Juneau Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Minerals And Geology
Project Activity:
Minerals Or Geology Plans Of Operations; Roadless Area Management
Current Status:
Cancelled
Forests:
Tongass National Forest
Districts:
Juneau Ranger District
States:
Alaska
Counties:
Juneau
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Curtis Caton
8510 Mendenhall Loop Road
Juneau, AK 99801
907-789-6273
curtislcaton@fs.fed.us