ADF&G (Fisheries) Unuk River Work Camp Amendment 2
Add clear plastic roof (removable) over porch on existing/approved tent platform (sleeping tent).
Project Summary
Location Summary:
Spring Camp Work Camp, approximately 8.5 miles up the Unuk River.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 01/12/2015 |
Decision | 01/2015 (Estimated) |
Implementation | 03/2015 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Tongass National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Decision Memo-ADF&G Fisheries Research Unuk River SUP Amendment #2
Decision Signed Date: 01/23/2015
Forests:
Tongass National Forest
Districts:
Ketchikan Misty Fjords Ranger District
States:
Alaska
Counties:
Ketchikan Gateway
Legal Land Description:
CRM, T. 66 S., R. 93 E., sec. 12
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jeannie Blackmore
Federal Building
Ketchikan, AK 99901
907-228-4120
jblackmore@fs.fed.us
Last Updated: 1/26/2015