FEC Line Replacement-Cascadilla
New powerline 1,00 feet and 30" wide
Project Summary
Location Summary:
Cascadilla along Middlefork of Flathead
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 08/01/2016 |
| Decision | 09/2016 (Estimated) |
| Implementation | 09/2016 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Hungry Horse Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Electric Transmission
Current Status:
Completed
Project Decision Information
FEC Line Replacement-Cascadilla
Decision Signed Date: 09/08/2016
Forests:
Flathead National Forest
Districts:
Hungry Horse Ranger District
States:
Montana
Counties:
Flathead
Legal Land Description:
NW 1/4, NE 1/4, Sec. 28, T31N, R17W
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Sadie Wehunt
10 Hungry Horse Drive
Hungry Horse, MT 59919
406-758-5364
sadieawehunt@fs.fed.us