Lion Lake Dam Repair
Leakage and declining integrity of the primary dam at Lion Lake was discovered. This project proposes repairing Lion Lake Dam.
Project Summary
Location Summary:
Lion Lake, approximately 1.5 miles south of Martin City, MT
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 03/08/2021 |
Decision | 06/2021 (Estimated) |
Implementation | 06/2021 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (7), 36 Cfr 220.6(E)(7)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Flathead National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Recreation Management; Watershed Management
Project Activity:
Developed Site Management; Watershed Improvements
Current Status:
Completed
Project Decision Information
Lion Lake Dam Repair
Decision Signed Date: 06/02/2021
Forests:
Flathead National Forest
Districts:
Hungry Horse Ranger District
States:
Montana
Counties:
Flathead
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jennifer Brady
650 Wolfpack Way
Kalispell, MT 59901
406-296-7175
jlbrady@fs.fed.us
Last Updated: 6/2/2021