Round Star Project
A project to reduce fuels, provide egress to local communities, improve diversity and resilience of vegetative communities, and contribute to the economy.
Project Summary
Location Summary:
Project is located on the northwest side of the Flathead Valley on the Tally Lake Ranger District.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 12/08/2021 |
Comment Period | 06/17/2022 |
Objection Period Start | 08/22/2022 |
Decision | 04/2024 (Estimated) |
Implementation | 06/2024 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Tally Lake Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Recreation Management; Forest Products; Vegetation Management (Other Than Forest Products); Fuels Management; Road Management
Project Activity:
Road Decommissioning; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Trail Management; Road Maintenance; Road Improvements/Construction; Timber Sales (Green)
Current Status:
Completed
Project Decision Information
Round Star Project
Decision Signed Date: 04/03/2024
Forests:
Flathead National Forest
Districts:
Tally Lake Ranger District
States:
Montana
Counties:
Flathead
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Ellen Mering
650 Wolfpack Way
Kalispell, MT 59901
406-758-3531
ellen.mering@usda.gov
Last Updated: 4/5/2024