Missoula Electric Cooperative Stoner Lake Road Line Extension
The project proposes to install approximately 5,700-feet of single-phase electrical underground line and 2 fiberglass junction boxes along National Forest System Roads 9780 (SEC 23, T20N, R17W) and 90240 (SEC 24, T20N, R17W).
Project Summary
Location Summary:
The project is located approximately 2.5 miles west of Swan Valley School, and just north of Stoner Lake, in Township 20 North, Range 17 West, Sections 23 and 24.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 04/10/2023 |
| Decision | 05/2023 (Estimated) |
| Implementation | 07/2023 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Swan Lake Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Electric Transmission
Current Status:
Completed
Project Decision Information
Missoula Electric Cooperative Stoner Lake Road Line Extension
Decision Signed Date: 05/11/2023
Forests:
Flathead National Forest
Districts:
Swan Lake Ranger District
States:
Montana
Counties:
Flathead
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Derek Milner
200 Ranger Station Road
Bigfork, MT 59911
406-758-5340
derek.milner@usda.gov
Last Updated: 5/11/2023