Moyie Meadow
Project Summary
Location Summary:
Moyie River and Meadow Creek County Roads, from Highway 2 north to Highway 95. Some powerline treatment proposed along Deer Creek and Perkins Lake Rd.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 10/29/2025 |
| Decision | 4/2026 (Estimated) |
| Implementation | 6/2026 (Estimated) |
Expected Analysis Type:
Categorical Exclusion
Lead Management Unit:
Bonners Ferry Ranger District
Project Purpose:
Forest products; Fuels management; Vegetation management (other than forest products)
Current Status:
Developing Proposal
Project Decision Information
Expected Decision Date: 4/2026 (Estimated)
States:
Idaho
Counties:
Boundary
Jennifer Anderson
c/o Bonners Ferry Ranger District
6286 Main St
Bonners Ferry, Idaho 83805
208-267-6749
jennifer.anderson3@usda.gov
Last Updated: 12/12/2025