Lines Creek BPA Electronic Site Expansion
This decision approves BPA's proposal to upgrade and expansion of the Lines Creek Electronic Site used to monitor the BPA transmission line.
Project Summary
Location Summary:
Map #8 - Lines Creek in the Bussel Creek drainage
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 05/29/2012 |
Comment Period | 05/29/2012 |
Decision | 09/2012 (Estimated) |
Implementation | 07/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Avery Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
BPA Lines Creek Electronic Site Expansion
Decision Signed Date: 09/11/2012
Legal Notice Date: 09/19/2012
Forests:
Idaho Panhandle National Forest
Districts:
Avery Ranger District
States:
Idaho
Counties:
Shoshone
Legal Land Description:
SW 1/4, SW 1/4, Section 33, T44N, R2E
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Lynette Myhre
HC Box 1
Avery, ID 83802-9702
208-245-6034
lmyhre@fs.fed.us
Last Updated: 9/20/2012