Million Dam spillway improvements
The proposed action is to replace the Million Dam earthen spillway approach section with concrete and then to stabilize the rip rap in the spillway channel
Project Summary
Location Summary:
Million Reservoir, approximately 3.5 miles southwest of South Fork, CO.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 03/23/2016 |
| Decision | 06/2017 (Estimated) |
| Implementation | 09/2017 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Divide Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Facility Management
Project Activity:
Facility Improvements/Construction; Facility Maintenance
Current Status:
Completed
Project Decision Information
Million Dam spillway improvements
Decision Signed Date: 06/19/2017
Forests:
Rio Grande National Forest
Districts:
Divide Ranger District
States:
Colorado
Counties:
Rio Grande
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Margaret Sullivan
13308 West Hwy 160
Del Norte, CO 81132
719-852-6246
margaretsullivan@fs.fed.us