Integrated - Jackson Mountain Landscape Project
Landscape level analysis of fuels reduction and vegetation managememt opportunities in Jackson Mountain area
Project Summary
Location Summary:
Jackson Mountain Area on the Pagosa Ranger District
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 01/10/2023 |
Comment Period | 06/27/2024 |
Objection Period Start | 11/14/2024 |
Decision | 01/2025 (Estimated) |
Implementation | 05/2025 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Pagosa Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Forest Products; Vegetation Management (Other Than Forest Products); Fuels Management
Project Activity:
Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Timber Sales (Green)
Current Status:
Completed
Project Decision Information
Jackson Mountain Landscape Project DN and FONSI
Decision Signed Date: 01/16/2025
Forests:
San Juan National Forest
Districts:
Pagosa Ranger District
States:
Colorado
Counties:
Archuleta
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Adam Tlachac
180 Pagosa Street, PO Box 310
Pagosa Springs, CO 81147
907-228-4126
adam.tlachac@usda.gov