Minerals - Catamount Spring Creek Gas Wells and Pipeline
Construction of an 8.4 mile pipeline system and the expansion of one existing gas well pad to facilitate re-completion of one existing gas well and horizontal drilling of seven new gas wells from the same pad.
Project Summary
Current Status:
Completed
Location Summary:
Spring Creek Road in the HD Mountains
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 10/18/2022 |
| Comment Period | 12/15/2023 |
| Objection Period Start | 06/26/2024 |
| Decision | 08/2024 (Estimated) |
| Implementation | 10/2024 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Forest Service Energy Implementation Plan
Lead Management Unit:
Columbine Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Minerals And Geology
Project Activity:
Special Use Authorizations; Minerals Or Geology Plans Of Operations
Project Decision Information
Minerals - Catamount Spring Creek Gas Wells and Pipeline
Decision Signed Date: 08/20/2024
Forests:
San Juan National Forest
Districts:
Columbine Ranger District
States:
Colorado
Counties:
Archuleta; La Plata
Legal Land Description:
T34N R6W
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
James Blair
367 Pearl Street
Bayfield, CO 81122
970-882-6856
James.Blair2@usda.gov
Last Updated: 8/20/2024