Special Uses - Clearnetworx Fiber Optic Cable Installation
Clearnetworx proposes to install fiber optic communications line between Dolores and Mancos. Approximately 882 linear feet would be installed on National Forest System lands.
Project Summary
Current Status:
Completed
Location Summary:
Along Highway 160 at Mancos Hill and southwest of the Town of Dolores.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 03/28/2025 |
| Decision | 06/2025 (Estimated) |
| Implementation | 06/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Mancos/Dolores Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Project Decision Information
Decision Memo - Clearnetworx Fiber Optic Cable Installation
Decision Signed Date: 06/03/2025
Forests:
San Juan National Forest
Districts:
Mancos/Dolores Ranger District
States:
Colorado
Counties:
Montezuma
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Emma Reinemann
29211 Highway 184
Dolores, CO 81323-9308
970-882-6822
emma.reinemann@usda.gov
Last Updated: 6/5/2025