Venus Basin Trail 641 Reconstruction and Maintenance
Approximately three miles of trail reconstruction on the exisitng alignment to restore the Venus Basin trail 641, damaged by the 2006 Little Venus Fire and maintenance on approximately seven miles of additional trail.
Project Summary
Location Summary:
Located in Venus Basin, Venus Creek drainage, Washakie WIlderness, west of Meeteetse, WY
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 06/10/2008 |
| Comment Period | 06/11/2008 |
| Decision | 06/2008 (Estimated) |
| Implementation | 07/2008 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (1), 36 Cfr 220.6(E)(1)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Greybull Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Recreation Management
Project Activity:
Trail Management
Current Status:
Completed
Project Decision Information
Venus Basin Trail Stabilization Project
Decision Signed Date: 06/11/2008
Legal Notice Date: 06/11/2008
Forests:
Shoshone National Forest
Districts:
Greybull Ranger District
States:
Wyoming
Counties:
Park
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Bill Oliver
203A Yellowstone Avenue
Cody, WY 82415
307-527-6921
boliver01@fs.fed.us