Renew Special Use Permits for Ten Communication Sites
Renew permits for ten communication sites on the Washakie and Wind River Ranger Districts.
Project Summary
Location Summary:
Limestone, Lava Mountain, Roundtop, Sheep Ridge, South Pass, Windy Ridge, and Copper Mountain communication sites.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 07/22/2013 |
| Decision | 09/2014 (Estimated) |
| Implementation | 10/2014 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Shoshone National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Decision Memo - Action Regarding Ten Communication Site Facilities
Decision Signed Date: 09/25/2014
Forests:
Shoshone National Forest
Districts:
Washakie Ranger District; Wind River Ranger District
States:
Wyoming
Counties:
Fremont
Legal Land Description:
T30N, R99W, secs. 18 & 30; T30N, R101W, sec.25; T40N, R93W, sec. 16; T41N, R107W, secs. 22 & 26; T43N, R110W, sec.23
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Daniel Aklufi
808 Meadow Lane Avenue
Cody, WY 82414
307-578-5151
daklufi@fs.fed.us
Last Updated: 9/26/2014