Rocky Mountain Power - Relocation Of Two Line Segments
Proposal to relocate two power line segments which cross/re-cross the North Fork of the Shoshone River. Replacement segments would be buried adjacent to the North Fork Highway (Highway 14/16/20) and would not cross the River.
Project Summary
Location Summary:
In the general vicinities of Fishhawk Trailhead and Big Game Campground, approximately 38.5 miles and 27.5 miles west of the city of Cody, respectively.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 02/18/2015 |
Decision | 08/2016 (Estimated) |
Implementation | 01/2017 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Shoshone National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Rocky Mountain Power - Relocation Of Two Line Segments
Decision Signed Date: 08/09/2016
Forests:
Shoshone National Forest
Districts:
Wapiti Ranger District
States:
Wyoming
Counties:
Park
Legal Land Description:
T52N, R106W, secs. 22-23; T52N, R108W, sec. 26.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Anita Harper
808 Meadow Lane Avenue
Cody, WY 82414
307-578-5228
anitaharper@fs.fed.us