Budworm Response Project
The proposal is to treat approximately 2,000 acres using a combination of vegetation management prescriptions including sanitation salvage, shelterwood/seed tree harvest prescription.
Project Summary
Location Summary:
Approximately 30 miles northwest of Cody, Wyoming along State Highway 296, Chief Joseph Scenic Byway.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 05/02/2016 |
| Comment Period | 11/15/2016 |
| Objection Period Start | 02/07/2018 |
| Decision | 04/2018 (Estimated) |
| Implementation | 05/2018 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Clarks Fork Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Vegetation Management (Other Than Forest Products); Forest Products
Project Activity:
Forest Vegetation Improvements; Timber Sales (Salvage); Timber Sales (Green)
Current Status:
Completed
Project Decision Information
Budworm Response Project
Decision Signed Date: 04/05/2018
Forests:
Shoshone National Forest
Districts:
Clarks Fork Ranger District
States:
Wyoming
Counties:
Park
Legal Land Description:
Township 56 North, Range 105 West, 6th Principal Meridian; Sections 9, 10, 14, 15, 16.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Amy Haas
203A Yellowstone Avenue
Cody, WY 82414
307-578-5237
ahaas@fs.fed.us
Last Updated: 4/24/2018