Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 09/14/2009 |
Decision | 10/2009 (Estimated) |
Implementation | 02/2010 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.12 (4), 36 Cfr 220.6(D)(4)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Sierra Vista Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Road Management
Project Activity:
Road Maintenance
Current Status:
Completed
Project Decision Information
Construction of Weirs at Road-Stream Crossings inSunnyside Canyon
Decision Signed Date: 10/14/2009
Forests:
Coronado National Forest
Districts:
Sierra Vista Ranger District
States:
Arizona
Counties:
Cochise
Legal Land Description:
T23S R19E Sec 21
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Brian Payne
5990 S. Hwy. 92
Hereford, AZ 85615
520-664-5436
bpayne@fs.fed.us
Last Updated: 10/21/2009