Forestwide Material Source Sites
Create material source sites to provide a more economic and better quality source of materials for various road and facility maintenance and improvement efforts such as road resurfacing, drainage improvements, and streambank stabilization.
Project Summary
Location Summary:
Multiple sites in multiple counties and Ranger Districts
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 11/20/2018 |
| Comment Period | 12/15/2021 |
| Objection Period Start | 09/21/2022 |
| Decision | 11/2022 (Estimated) |
| Implementation | 12/2022 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Coronado National Forest All Units
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Road Management
Project Activity:
Road Maintenance
Current Status:
Completed
Project Decision Information
Forestwide Material Source Sites
Decision Signed Date: 11/18/2022
Forests:
Coronado National Forest
Districts:
Coronado National Forest All Units
States:
Arizona
Counties:
Cochise; Graham; Pima; Pinal; Santa Cruz
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Emily Reynolds
300 W. Congress Street
Tucson, AZ 85701
520-388-8311
Emily.Reynolds@usda.gov
Last Updated: 11/18/2022