Recreation Residence Cabin Modification Lot 80, Turkey Flat
Modifications proposed for Lot 80 of Turkey Flat including the addition of a bathroom, addition of a bedroom, add roof over the remaining portion of the concrete slab deck. Pit toilet will be removed due to indoor toilet.
Project Summary
Location Summary:
Lot 80, Turkey Flat Tract, Pinaleno Ecosystem Management Area, Graham County, AZ
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 01/21/2020 |
Decision | 05/2020 (Estimated) |
Implementation | 06/2020 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Safford Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Cabin Modification for Lot 80, Turkey Flat
Decision Signed Date: 05/29/2020
Forests:
Coronado National Forest
Districts:
Safford Ranger District
States:
Arizona
Counties:
Graham
Legal Land Description:
T.9 S., R. 25E., Section 20
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Alysa Hansen
P.O. Box 709
Safford, AZ 85548-0709
520-388-8432
alysa.hansen@usda.gov
Last Updated: 6/3/2020