Parker Canyon Lake Improvement
Implementation of AZGF's grant funded project to expand parking, improve traffic flow, and add a boat ramp at Parker Canyon Lake. Includes replacement of a failing culvert that drains an intermittent stream between lake access and nearby campgrounds.
Project Summary
Location Summary:
From the intersection of Interstate and State Route 83, take State Route south 53 miles to Parker Canyon Lake.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 12/27/2022 |
| Decision | 05/2023 (Estimated) |
| Implementation | 09/2023 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (22), 36 Cfr 220.6(E)(22)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Coronado National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Road Management; Recreation Management
Project Activity:
Developed Site Management; Trail Management; Road Improvements/Construction
Current Status:
Completed
Project Decision Information
Parker Canyon Lake Improvement
Decision Signed Date: 05/31/2023
Forests:
Coronado National Forest
Districts:
Sierra Vista Ranger District
States:
Arizona
Counties:
Cochise
Legal Land Description:
Township 23S, Range 19E, Section18
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Emily Reynolds
300 W. Congress Street
Tucson, AZ 85701
5203888311
Emily.Reynolds@usda.gov
Last Updated: 5/31/2023