Zia Natural Gas Pipeline at Cedar Creek Road
Installation of a two inch pipeline under Cedar Creek Road at the corner of Mechem Drive (HWY 48) and Cedar Creek Road in Ruidoso to improve access to natural gas for nearby subdivisions.
Project Summary
Location Summary:
At the corner of Mechem Drive (HWY 48) and Cedar Creek Road in Ruidoso
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 05/04/2012 |
Comment Period | 05/04/2012 |
Decision | 07/2012 (Estimated) |
Implementation | 07/2012 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Smokey Bear Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Install Zia Natural Gas Pipeline at Cedar Creek Road
Decision Signed Date: 07/17/2012
Install Zia Natural Gas Pipeline at Cedar Creek Road
Decision Signed Date: 07/17/2012
Forests:
Lincoln National Forest
Districts:
Smokey Bear Ranger District
States:
New Mexico
Counties:
Lincoln
Legal Land Description:
T11S, R13E, Section 16
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Eric Turbeville
901 Mechem Drive
Ruidoso, NM 88345
575-630-3051
eturbeville@fs.fed.us
Last Updated: 7/17/2012