Diamond Peak Pipeline Improvements
Install a 1 mile pipeline from an existing well on private land to a new storage tank and drinker on the Diamond Peak Allotment. The drinker will have an overflow to provide drinking water to wildlife where reliable water is currently unavailable.
Project Summary
Location Summary:
Diamond Peak Allotment--adjacent to but not within the White Mountain Wilderness Area
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 06/20/2016 |
Decision | 07/2016 (Estimated) |
Implementation | 08/2016 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (6), 36 Cfr 220.6(E)(6)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Smokey Bear Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Wildlife, Fish, Rare Plants; Grazing Management
Project Activity:
Species Habitat Improvements; Grazing Structural Improvements
Current Status:
Completed
Project Decision Information
Diamond Peak Pipeline Improvements
Decision Signed Date: 07/29/2016
Forests:
Lincoln National Forest
Districts:
Smokey Bear Ranger District
States:
New Mexico
Counties:
Lincoln
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
George Douds
901 Mechem Drive
Ruidoso, NM 88345
575-257-4095
gdouds@fs.fed.us
Last Updated: 7/29/2016