Carrissa Storage and Pipeline off Monument Spring
The proposed action is to construct a new storage tank on approximately 10 miles of above ground replacement pipeline. The pipeline would begin on the Agua Chiquita allotment and end on the Carrissa allotment.
Project Summary
Location Summary:
This project is located in T. 19 S., R. 13 E., Sections 15-23 & 25-36; T. 19 S., R. 14 E., Sections 31-32; T. 20 S., R. 13 E., Sections 4-11, 14-16, 23.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 09/26/2018 |
Decision | 02/2021 (Estimated) |
Implementation | 02/2021 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (9), 36 Cfr 220.6(E)(9)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Sacramento Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Grazing Management
Project Activity:
Grazing Allotment Management
Current Status:
Cancelled
Forests:
Lincoln National Forest
Districts:
Sacramento Ranger District
States:
New Mexico
Counties:
Otero
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Shawna Allen
P.O. Box 288
Cloudcroft, NM 88317
575-682-5321
slallen@fs.fed.us