Cedar Creek Trailhead and Water Crossing Reconstruction 2024
Reconstruction of the main Cedar Creek Trailhead which would include expanding and surfacing the parking areas and installing two restrooms, utility lines, and other features. Planning to construct a vented ford water crossing across Cedar Creek.
Project Summary
Location Summary:
Project located along Cedar Creek Drive on the west side of Ruidoso, New Mexico.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 03/11/2024 |
| Decision | 04/2024 (Estimated) |
| Implementation | 06/2024 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (22), 36 Cfr 220.6(E)(22)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Smokey Bear Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Recreation Management
Project Activity:
Developed Site Management
Current Status:
Completed
Project Decision Information
Cedar Creek Trailhead and Water Crossing Reconstruction 2024
Decision Signed Date: 04/22/2024
Forests:
Lincoln National Forest
Districts:
Smokey Bear Ranger District
States:
New Mexico
Counties:
Lincoln
Legal Land Description:
Section 16, T. 11 S., R. 13 E., NMPM
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Marcie Kelton
901 Mechem Drive
Ruidoso, NM 88345
575-682-2551
marcie.kelton@usda.gov
Last Updated: 4/23/2024