Interstate 17 Corridor Wireless Communications Improvements Antelope Telecommunications Site
The Antelope communications site proposal was developed as part of a wireless communications system that will improve the reliability and capacity of wireless telecommunications for the I-17 corridor.
Project Summary
Current Status:
Completed
Location Summary:
NW1/4 SE1/4 Section 3, T. 12 N., R. 3 E., G&SRM, Yavapai County, AZ
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 04/01/2021 |
| Decision | 10/2021 (Estimated) |
| Implementation | 11/2021 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Verde Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Project Decision Information
Interstate 17 Corridor Wireless Communications Improvements Antelope Telecommunications Site
Decision Signed Date: 10/05/2021
Forests:
Prescott National Forest
Districts:
Verde Ranger District
States:
Arizona
Counties:
Yavapai
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Christopher Welker
300 East HWY 260
Camp Verde, AZ 86322
928-443-8072
chris.welker@usda.gov
Last Updated: 3/15/2022