Draconis Energy Project, LLC and 7x Energy, Inc. 500 kV electric transmission line
Issuance of a Special Use Permit (SUP) to Draconis Energy Project, LLC (Draconis) for access to areas of the Prescott National Forest, Bradshaw and Chino Ranger District (PNF, BRD/CRD) to support electric transmission line construction.
Project Summary
Location Summary:
N1/2 Section 22 and NW1/4 Section 23, T. 16 N., R. 1 E, G&SRM, Yavapai County, Arizona.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 02/2024 (Estimated) |
Decision | 09/2024 (Estimated) |
Implementation | 10/2024 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Prescott National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Electric Transmission; Special Use Authorizations
Current Status:
Cancelled
Forests:
Prescott National Forest
Districts:
Bradshaw Ranger District
States:
Arizona
Counties:
Yavapai
Legal Land Description:
N1/2 Section 22 and NW1/4 Section 23, T. 16 N., R. 1 E, G&SRM, Yavapai County, Arizona.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Christopher Welker
344 So. Cortez St.
Prescott, AZ 86303
928-443-8072
Christopher.Welker@usda.gov
Last Updated: 4/1/2025