APS Prescott to Mingus & Yavapai 69kV Sub-Transmission Lines
The Forest Service proposes to re-issue to Arizona Public Service Company the special use permit for continued operation of the Prescott to Mingus & Yavapai P-26-O, 69kV sub-transmission line that has been in operation since 1950.
Project Summary
Location Summary:
Line runs for approximately 10 miles from Prescott to Mingus Mtn and Yavapai Ranch
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 08/01/2009 |
Decision | 11/2009 (Estimated) |
Implementation | 11/2009 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (15)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Verde Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
APS Prescott to Mingus & Yavapai 69kV Sub-Tansmission LInes
Decision Signed Date: 11/10/2009
Forests:
Prescott National Forest
Districts:
Chino Valley Ranger District; Verde Ranger District
States:
Arizona
Counties:
Yavapai
Legal Land Description:
T15N, R2E, Sects 4,5,7,8,18; T16N, R2E, Sects 24,28,32,33; and T16N, R2E, Sects 23,26,35,36.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Sheila Sandusky
P.O. Box 670
Camp Verded, AZ 86322-0670
928-214-2455
ssandusky@fs.fed.us
Last Updated: 10/19/2010