Poland Junction Substation 50-year Permit
The Forest Service proposes to issue a permit for the Poland Junction Substation. The substation was previously permitted in conjunction with the Childs 69kV subtansmission line.
Project Summary
Location Summary:
Approximately 10 miles southeast of the city of Prescott of FR 667.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 08/09/2010 |
Decision | 10/2010 (Estimated) |
Implementation | 12/2010 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Prescott National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Poland Junction Substation 50-year Permit
Decision Signed Date: 10/29/2010
Forests:
Prescott National Forest
Districts:
Bradshaw Ranger District
States:
Arizona
Counties:
Yavapai
Legal Land Description:
T12N, R1E, SE ¼ of the NE ¼ of Section 5
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Sheila Sandusky
344 So. Cortez St.
Prescott, AZ 86303
928-214-2455
ssandusky@fs.fed.us
Last Updated: 11/8/2010