Century Link Buried Fiber Optic Project- Drake to North Boundary
The Prescott National Forest intends to authorize Century Link to bury a fiber optic cable in an existing utility corridor between Drake and the forest's northern boundary with the Kaibab NF>
Project Summary
Location Summary:
From Drake to northern forest boundary with Kaibab NF along Transwestern corridor.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 01/04/2016 |
Decision | 01/2016 (Estimated) |
Implementation | 04/2016 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Chino Valley Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Century Link Buried Fiber Optic Project- Drake to North Boundary
Decision Signed Date: 01/06/2016
Forests:
Prescott National Forest
Districts:
Chino Valley Ranger District
States:
Arizona
Counties:
Yavapai
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Richard Della Porta
735 N. Hwy. 89
Chino Valley, AZ 86323-0485
928-443-8013
rdellaporta@fs.fed.us
Last Updated: 1/7/2016