Oak Wash WRAP EP10
Mitigate OHV and dispersed recreation use impacts in the Slaughter House FR359 area through the closure and rehabilitation of unauthorized roads, the demolition and removal of the Slaughter House structure, and the installation of signage.
Project Summary
Location Summary:
Slaughter House FR359 area
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 08/25/2017 |
Decision | 11/2017 (Estimated) |
Implementation | 12/2017 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (20), 36 Cfr 220.6(E)(20)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Verde Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Watershed Management
Project Activity:
Watershed Improvements
Current Status:
Completed
Project Decision Information
Oak Wash WRAP EP10
Decision Signed Date: 11/16/2017
Forests:
Prescott National Forest
Districts:
Verde Ranger District
States:
Arizona
Counties:
Yavapai
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
David Moore
P.O. Box 670
Camp Verded, AZ 86322-0670
928-443-8179
dmoore05@fs.fed.us
Last Updated: 11/16/2017