Greater Prescott Trails Mid-Term Projects #2
This project will analyze and evaluate the existing and proposed motorized trail system for the Greater Prescott Trails Plan project area focusing primarily on the Seven Mile Gulch area.
Project Summary
Location Summary:
Greater Prescott Basin with a primary focus on Seven Mile Gulch area.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 01/19/2018 |
Comment Period | 11/10/2018 |
Objection Period Start | 05/15/2020 |
Decision | 10/2020 (Estimated) |
Implementation | 11/2020 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Bradshaw Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Recreation Management
Project Activity:
Trail Management; Travel Management
Current Status:
Completed
Project Decision Information
Greater Prescott Trails Mid-Term Projects #2
Decision Signed Date: 10/15/2020
Forests:
Prescott National Forest
Districts:
Bradshaw Ranger District
States:
Arizona
Counties:
Yavapai
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Susan Johnson
344 South Cortez Street
Prescott, AZ 86303-4398
928-443-8075
sajohnson@fs.fed.us
Last Updated: 10/16/2020