Arizona Public Service Amendment #1 to Master Special Use Permit PNF142
Amendment to the Master SUP issued to APS for all electric transmission and distribution lines up 33 kV capacity is necessary to include the new underground distribution line within the C120 road prism as part of APS's electric service area.
Project Summary
Location Summary:
Prescott Basin Geographical Management Area as depicted in the 2015 Prescott N.F. Forest Plan
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 02/08/2019 |
Decision | 02/2019 (Estimated) |
Implementation | 03/2019 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Prescott National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Arizona Public Service Amendment #1 to Master Special Use Permit PNF142
Decision Signed Date: 02/14/2019
Forests:
Prescott National Forest
Districts:
Bradshaw Ranger District
States:
Arizona
Counties:
Yavapai
Legal Land Description:
SW1/4 SE1/4 Section 15 and W1/2 NE1/4 Section 22, T. 14 N., R. 3 W., Gila & Salt River Meridian,Yavapai County, Arizona
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Chris Welker
344 So. Cortez St.
Prescott, AZ 86303
928-443-8072
cwelker@fs.fed.us
Last Updated: 7/15/2019