Resumidero Campground Improvement Project
Capital Improvement project on the Resumidero Campground. Drinking water, waste/trash facilities, equistrian corrals, camp sites and group facilities.
Project Summary
Location Summary:
Coyote Ranger District/Santa Fe National Forest
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 08/27/2004 |
Comment Period | 08/11/2005 |
Decision | 07/2008 (Estimated) |
Implementation | 10/2008 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Coyote Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Recreation Management
Project Activity:
Developed Site Management; Facility Improvements/Construction; Dispersed Recreation Mgmt.
Current Status:
Completed
Project Decision Information
Resumidero Campground Improvement Project
Decision Signed Date: 07/31/2008
Legal Notice Date: 08/21/2008
Forests:
Santa Fe National Forest
Districts:
Coyote Ranger District
States:
New Mexico
Counties:
Rio Arriba
Legal Land Description:
T22N, R2E. section 29
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Chris Napp
P.O. Box 160
Coyote, NM 87012
505-438-7820
cnapp@fs.fed.us
Last Updated: 9/30/2008