APS 69kv Power Line Permit for Childs-Irving Line
Issuance of a permit to replace the expired Federal Energy Regulatory Commission Hydropower License. Existing 69 kV line that was part of the Childs Irving Power operation and covered under the old license. Has been in continuous operation.
Project Summary
Location Summary:
Line that travels from Childs substation to Irving power plant area. Includes small sections of the Tonto NF where it crosses Fossil Creek.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 08/12/2015 |
Decision | 08/2023 (Estimated) |
Implementation | 08/2023 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.12 (10)
Special Authority:
Forest Service Energy Implementation Plan
Lead Management Unit:
Red Rock Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Electric Transmission; Special Use Authorizations
Current Status:
Cancelled
Forests:
Coconino National Forest; Tonto National Forest
Districts:
Red Rock Ranger District; Payson Ranger District
States:
Arizona
Counties:
Gila; Yavapai
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Mike Dechter
8375 State Route 179
Sedona, AZ 86351
928-527-3416
Michael.Dechter@usda.gov
Last Updated: 6/29/2023