Resolution Copper Project and Land Exchange
Objections to draft ROD must be submitted within 45 calendar days following publication of legal notice in Arizona Capitol Times. The agency published the final environmental impact statement in the Federal Register on June 20, 2025. For additional information, please go to: https://www.resolutionmineeis.us/
Project Summary
Location Summary:
Tonto National Forest
Project Milestones:
| Milestone | Date |
|---|---|
| NOI in Federal Register | 03/18/2016 |
| DEIS NOA in Federal Register | 08/09/2019 |
| FEIS NOA in Federal Register | 06/20/2025 |
| Objection Period Start | 06/20/2025 |
| Decision | 12/2025 (Estimated) |
| Implementation | 01/2026 (Estimated) |
Expected Analysis Type:
Environmental Impact Statement
Special Authority:
Not Applicable / Other
Lead Management Unit:
Tonto National Forest All Units
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Minerals And Geology; Land Ownership Management
Project Activity:
Minerals Or Geology Plans Of Operations; Plan Amendment; Land Exchanges
Current Status:
In Progress
Forests:
Tonto National Forest
Districts:
Globe Ranger District; Mesa Ranger District
States:
Arizona
Counties:
Pinal
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Michelle Tom
2324 East McDowell Road
Phoenix, AZ 85006
602-225-5200
comments-southwestern-tonto@usda.gov
Last Updated: 6/20/2025