Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 05/09/2018 |
Decision | 05/2018 (Estimated) |
Implementation | 06/2018 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Cave Creek Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Road Management; Special Use Management; Facility Management
Project Activity:
Developed Site Management; Facility Improvements/Construction; Special Use Authorizations; Facility Maintenance
Current Status:
Cancelled
Forests:
Tonto National Forest
Districts:
Cave Creek Ranger District
States:
Arizona
Counties:
Maricopa
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jeffrey Sturla
40202 N. Cave Creek Road
Scottsdale, AZ 85262
480-595-3331
comments-southwestern-tonto-cave-creek@fs.fed.us
Last Updated: 3/6/2019