Pinal Mountain Transmission Line Reconstruction
The Tonto National Forest is proposing to authorize the replacement of approximately 3.9 miles of 21kV power line that serves the Pinal Peak communications & fire lookout site by Arizona Public Service (APS). Public comment period ends April 15, 2013
Project Summary
Location Summary:
North slope of Pinal Mountains
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 02/14/2013 |
| Comment Period | 03/13/2013 |
| Decision | 06/2013 (Estimated) |
| Implementation | 07/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Tonto National Forest All Units
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Pinal Mountain Transmission Line Reconstruction
Decision Signed Date: 06/03/2013
Legal Notice Date: 06/07/2013
Forests:
Tonto National Forest
Districts:
Globe Ranger District
States:
Arizona
Counties:
Gila
Legal Land Description:
GSRM T. 1 S., R. 15 E., Sections 21, 22, 28 and 33,
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Mark McEntarffer
2324 East McDowell Road
Phoenix, AZ 85006
602-225-5239
mmcentarffer@fs.fed.us
Last Updated: 12/10/2019