Bar X 2011 Pipeline Extensions
Extensions of three existing pipelines to storage tanks and livestock/wildlife drinkers. Pipelines would primarily follow existing FS roads; storage units and drinkers would be located on large, flat, rocky sites minimizing ground disturbance.
Project Summary
Location Summary:
Pleasant Valley Ranger District, Bar X Allotment Complex, Windmill Pasture, Lower Dry Creek Pasture and Bar X Pasture
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 06/08/2011 |
Decision | 06/2011 (Estimated) |
Implementation | 08/2011 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (9), 36 Cfr 220.6(E)(9)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Pleasant Valley Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Grazing Management
Project Activity:
Grazing Structural Improvements
Current Status:
Completed
Project Decision Information
Bar X 2011 Pipeline Extensions
Decision Signed Date: 06/20/2011
Forests:
Tonto National Forest
Districts:
Pleasant Valley Ranger District
States:
Arizona
Counties:
Gila
Legal Land Description:
From T9N, R14E, Sec. 18 to T9N, R13E, Sec. 12; From T10N, R13E, Sec. 25 to T10N, R 14E, Sec. 30; Within T 10 N, R 13 E, Sec. 24
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Donal Luhrsen
P.O. Box 450
Young, AZ 85554
602-225-5222
dluhrsen@fs.fed.us
Last Updated: 1/6/2012