Potato Butte 2011 Juniper Treatment
Approximately 900 acres of alligator juniper encroachment would be mechanically removed with a skid-steer mounted agri-axe. Project area is on gentle slopes in semi-desert grasslands & project specifications would result in minimal soil disturbance.
Project Summary
Location Summary:
T 9 N, R 13 E, Corner of Sections 21, 22, 27 & 28; and T 9 N, R 13 E, Corner of Sections 33 & 34
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 06/09/2011 |
Comment Period | 06/09/2011 |
Decision | 08/2011 (Estimated) |
Implementation | 08/2011 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (6), 36 Cfr 220.6(E)(6); 32.2 (9), 36 Cfr 220.6(E)(9)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Tonto National Forest All Units
Notice and Comment Regulation:
215
Project Purpose:
Watershed Management; Vegetation Management (Other Than Forest Products); Grazing Management
Project Activity:
Forest Vegetation Improvements; Grazing Allotment Management; Rangeland Vegetation Improvements; Watershed Improvements
Current Status:
Completed
Project Decision Information
Potato Butte 2011 Juniper Treatment
Decision Signed Date: 08/11/2011
Forests:
Tonto National Forest
Districts:
Pleasant Valley Ranger District
States:
Arizona
Counties:
Gila
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Donna Reed
2324 East McDowell Road
Phoenix, AZ 85006
760-873-2450
dlreed@fs.fed.us
Last Updated: 8/26/2011