Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 03/23/2012 |
Comment Period | 10/19/2012 |
Decision | 01/2013 (Estimated) |
Implementation | 03/2013 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Tonto National Forest All Units
Notice and Comment Regulation:
215
Project Purpose:
Land Management Planning
Project Activity:
Plan Creation/Revision
Current Status:
Completed
Project Decision Information
Issuance of Priority Outfitter-guide Permits and Forest Plan Amendment
Decision Signed Date: 01/08/2013
Legal Notice Date: 01/11/2013
Forests:
Tonto National Forest
Districts:
Tonto National Forest All Units
States:
Arizona
Counties:
Gila; Maricopa; Pinal; Yavapai
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Rachel Franchina
2324 East McDowell Road
Phoenix, AZ 85006
970-819-2507
rfranchina@fs.fed.us
Last Updated: 2/14/2013