Sunflower Well Pipeline Project
This project will entail the conveyance of water from an existing private well to a new 10,000 underground storage tank. HDPE pipe will carry water from the tank to two new 500 gallon troughs. Project will improve livestock distribution.
Project Summary
Location Summary:
Project is located within the Diamond Pasture of the Diamond Allotment.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 12/14/2011 |
| Comment Period | 05/11/2012 |
| Decision | 10/2012 (Estimated) |
| Implementation | 12/2012 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (9), 36 Cfr 220.6(E)(9)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Mesa Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Grazing Management; Vegetation Management (Other Than Forest Products); Watershed Management
Project Activity:
Grazing Structural Improvements
Current Status:
Completed
Project Decision Information
Sunflower Well Pipeline Project
Decision Signed Date: 10/25/2012
Legal Notice Date: 10/26/2012
Forests:
Tonto National Forest
Districts:
Mesa Ranger District
States:
Arizona
Counties:
Maricopa
Legal Land Description:
T6N R8E Section 25; T6N R9E Sections 7, 18, 19, 30.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Kelly Kessler
5140 E. Ingram St.
Mesa, AZ 85205
480.610.3305
kmkessler@fs.fed.us
Last Updated: 12/10/2019