Storm Canyon Fence Line, Miners Camp Pipeline
Fenceline will divide Storm Canyon Pasture and be constructed of all metal materials. WIndmill, 3 troughs, and a storage tank will be placed along 1 mile of pipeline to increase livestock distribution and provide water for livestock and wildlife.
Project Summary
Location Summary:
Sedow Allotment on Globe Ranger District
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 11/15/2011 |
Comment Period | 11/16/2011 |
Decision | 09/2012 (Estimated) |
Implementation | 10/2012 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Globe Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Vegetation Management (Other Than Forest Products); Grazing Management
Project Activity:
Facility Improvements/Construction; Grazing Allotment Management; Grazing Authorizations; Rangeland Vegetation Improvements; Grazing Structural Improvements
Current Status:
Completed
Project Decision Information
Miner
Decision Signed Date: 09/21/2012
Legal Notice Date: 09/25/2012
Forests:
Tonto National Forest
Districts:
Globe Ranger District
States:
Arizona
Counties:
Gila
Legal Land Description:
T3N, R16E, Sec 8; T4N, R16E, Sec 4,5, 6, 8, 31, and 33 Gila and Salt River Meridian.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Andrea Wages
768 S. Sixshooter Canoyon Rd.
Globe, AZ 85501
928-402-6222
ajwages@fs.fed.us
Last Updated: 9/28/2012