Plan of Operations for Imerys Perlite Mine
Consolidates previous Plan of Operation and Special Use Permit authorizations, including continued operation of existing sedimentation basin; Use of segments of Forest Roads 229, 989, and 2403 for hauling; and mining at two unpatented claims.
Project Summary
Location Summary:
Superior, Arizona
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 12/03/2013 |
Comment Period | 01/14/2015 |
Objection Period Start | 07/15/2015 |
Decision | 07/2015 (Estimated) |
Implementation | 10/2015 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Globe Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Minerals And Geology
Project Activity:
Minerals Or Geology Plans Of Operations
Current Status:
Completed
Project Decision Information
IMERYS Perlite Mine, USA Inc. Project Plan of Operations
Decision Signed Date: 07/15/2015
Forests:
Tonto National Forest
Districts:
Globe Ranger District
States:
Arizona
Counties:
Pinal
Legal Land Description:
Township 2 South, Range 12 East, Sections 4 and 9
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Lee Ann Atkinson
768 S. Sixshooter Canoyon Rd.
Globe, AZ 85501
928-402-6281
leeannatkinson@fs.fed.us
Last Updated: 7/16/2015