Utah Communications Authority East Park Communications Site Project
The Ashley NF would issue a new 30-year special use permit to Utah Communications Authority for existing infrastructure at the East Park communications site. The new permit would replace the existing permit issued to the State of Utah.
Project Summary
Current Status:
Completed
Location Summary:
Northeast of East Park reservoir located on Forest Service Road 10021 at the East Park Communication Site.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 04/30/2021 |
| Decision | 12/2021 (Estimated) |
| Implementation | 12/2021 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Ashley National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Project Decision Information
Utah Communications Authority East Park Communications Site Project
Decision Signed Date: 12/15/2021
Forests:
Ashley National Forest
Districts:
Flaming Gorge Ranger District
States:
Utah
Counties:
Daggett
Legal Land Description:
SW1/4N/W1/4N/W1/4OF sec, 12 T.1N.,R.21E, Salt Lake Meridian Utah
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Rhett Burkman
355 North Vernal Ave
Vernal, UT 84078
435-781-5133
rhett.burkman@usda.gov
Last Updated: 12/21/2021